June 26 – July 10, 2015

Waukegan Road to Bridge.   The contractor is working on the Phase III center median and left turn lanes.  This includes pavement removal, curb and gutter installation, left turn pavement, and irrigation system installation.  The permanent traffic signal work is also underway.  Signal work will start at Waukegan Road and will proceed east to the other intersections along the corridor.       

Bridge to Happ.  The contractor is in the process of installing the brick sidewalks in the downtown area.  While that work is underway, traffic will remain on the north side of the right of way.

Happ Road Detour Alert.   The Happ Road intersection has been re-opened ahead of schedule.

Eden’s to East Limits.  Final sidewalk, curbs, and driveway installations are underway and will continue to occur in conjunction with other similar work along the corridor.  

 

The detailed construction work and traffic conditions can be tracked at http://northfieldwillowroad.blogspot.com/ ; through Facebook at Willow Road Construction Project; or through Twitter at @willowroadcp.   Actual start dates and activities may change due to weather or other conflicts.   #willowroadcp