Friday, June 26, 2015

Willow Road Work Plan

June 26 – July 10, 2015

Waukegan Road to Bridge.   The contractor is working on the Phase III center median and left turn lanes.  This includes pavement removal, curb and gutter installation, left turn pavement, and irrigation system installation.  The permanent traffic signal work is also underway.  Signal work will start at Waukegan Road and will proceed east to the other intersections along the corridor.       

Bridge to Happ.  The contractor is in the process of installing the brick sidewalks in the downtown area.  While that work is underway, traffic will remain on the north side of the right of way.

Happ Road Detour Alert.   The Happ Road intersection has been re-opened ahead of schedule.

Eden’s to East Limits.  Final sidewalk, curbs, and driveway installations are underway and will continue to occur in conjunction with other similar work along the corridor.  

 

The detailed construction work and traffic conditions can be tracked at http://northfieldwillowroad.blogspot.com/ ; through Facebook at Willow Road Construction Project; or through Twitter at @willowroadcp.   Actual start dates and activities may change due to weather or other conflicts.   #willowroadcp

Wednesday, June 17, 2015

Detour Alert – Happ Road

On Monday, June 22, 2014 IDOT plans to close the southern intersection of Willow Road and Happ Road to install the center roadway improvements.  The Happ Road intersection is expected to be closed for one week and is tentatively set to re-open on Saturday, June 27.   Traffic will be detoured west to Northfield Road and local traffic will be able to access the downtown on Walnut Street.        

Click here to see the detour route

http://www.northfieldil.org/E-News/Happ_Road_Detour.pdf

During the detour period the Village will:

  • monitor the intersections, and will request signal timing adjustments, if needed, to minimize traffic backups;
  • provide special Police patrols on local streets to reduce speeding and cut through traffic; and, 
  • ensure emergency responses routes are maintained to all part of the community for police, fire and ambulance access.  

 Detailed construction work and current traffic conditions can be tracked at http://northfieldwillowroad.blogspot.com/ ; through Facebook at Willow Road Construction Project; or through Twitter at @willowroadcp.   Please note that the actual start dates and activities may change due to weather or other conflicts.  #willowroadcp 

Friday, June 12, 2015

Willow Road Work Plan

June 12-26, 2015

Waukegan Road to Bridge.  The east and west lane pavements are substantially complete in this area.  The contractor is working on the final grading, curb and gutter, driveways, and sidewalk.  As soon as that work is complete, the pavement will be restriped and traffic will be adjusted.  The contractor will then begin the final stage of center median and turn lane work.  The traffic changeover is anticipated the week of June 15th.   

Bridge to Happ.  The contractor will continue to work on the signal and lighting foundations, brick sidewalk, curb and gutter, and driveway installations on the south side of the right of way.  While that work is underway, traffic will remain on the north side of the right of way in the downtown area.

Happ Road Detour Alert.   A week long detour is anticipated to commence, on the southern leg of the Happ/Central intersection.  The contractor will be working to construct the left turn lanes and center intersection pavements.  Traffic will be detoured to Northfield road but will also be able to access the downtown via Walnut.  When an actual start date is confirmed a special detour notice will be posted.  Click here to see the planned detour route.     http://www.northfieldil.org/E-News/Happ_Road_Detour.pdf

Eden’s to East Limits.  Final sidewalk, curbs, and driveway installations are underway and will continue to occur in conjunction with other similar work along the corridor.   

The detailed construction work and traffic conditions can be tracked at http://northfieldwillowroad.blogspot.com/ ; through Facebook at Willow Road Construction Project; or through Twitter at @willowroadcp.   Actual start dates and activities may change due to weather or other conflicts.   #willowroadcp