Friday, April 26, 2013

Willow Road Construction Process

 

To help you follow the progress of the Willow Road redevelopment project, we want to explain in detail IDOT’s plan.  Construction will proceed in phases with the goals of maximizing efficiency and safety for pedestrians and motorists, alike. Throughout the two-year construction period, IDOT’s plan is to keep at least one lane of traffic open in each direction throughout the corridor.  The following is a brief overview of how IDOT plans to phase the improvements:

• Pre-Phase I – Preparation Work

This work is currently underway and includes relocating the underground and overhead utilities that are in conflict with the project; installing temporary traffic signals at each intersection; removing trees, medians or other conflicts along the corridor; installing erosion control measures and other fencing to protect the work zone and adjacent properties; and finally, installing a temporary lane/pavement on the south side of the roadway to allow one lane of traffic to remain open both east and west bound.   Once completed, Phase I work begins.

• Phase I – North Side Construction 

During this initial construction phase, temporary traffic controls and barricades will be installed to shift all of the traffic, both pedestrian and vehicular, to the south side of the corridor.   The contractor will then work on the north side of the project to install the utilities, curbs and gutter, storm water system, roadway and sidewalks.  Once completed, Phase II work begins.

• Phase II – South Side Construction 

During this next phase of work, the temporary traffic controls and barricades will be relocated and the traffic, both pedestrian and vehicular, will be shifted to the newly constructed north side of the corridor.   The contractor will then work on the south side of the project to install the utilities, curbs and gutter, storm water system, roadway and sidewalks.  Once completed, Phase III work begins.

• Phase III – Center Construction 

During this final phase of roadway work, the temporary traffic controls and barricades will be relocated, and the vehicular traffic will be shifted so that the westbound traffic is on the far north side of the corridor and the eastbound traffic is on the far south side of the corridor.   During this phase, the pedestrian sidewalks will be open on both sides of the street.   The contractor will then install the center medians and the curbs, gutter and roadway in the center portion of the corridor.  Once completed, Phase IV final restoration work begins.

• Phase IV – Restoration 

During this final phase of work, the contractor will complete the final grading; place new top soil and seed; install 569 new trees, 848 shrubs, and about 11,000 perennials in the parkway and medians; and complete all of the final finishes including the decorative bridge and lighting details in the Village Center.

This multi-phase process is expected to take about two years to complete.  The roadway and sidewalk work is scheduled to be completed by the end of 2014, and then the planting and restoration work will take place immediately following in the spring of 2015.  Regular updates will be available throughout the construction process.  To follow the progress and monitor traffic conditions please check in at http://northfieldwillowroad.blogspot.com/ or on Facebook at Willow Road Construction Project or Twitter @willowroadcp.

Friday, April 19, 2013

What's New for Willow Road

For April 22 to May 3, 2013

At the April 17, 2013 Willow Road coordination meeting IDOT and Lorig Construction provided their proposed construction schedule for the next two weeks. The work planned includes:

Weeks of April 22nd & 29th

  • Utility companies such as Com Ed, Comcast and NICOR will continue their work relocating utilities that are in conflict with the new roadway.
  • The general contractor, Lorig Construction will continue to install erosion control measures to ensure that silt and other debris is not washed away into adjacent properties or waterways; they will be installing the temporary traffic signals at the intersections, starting on the west end of the project at Waukegan and Willow; and will then start removing the existing landscape medians.

More detailed construction work and traffic conditions can be tracked at http://northfieldwillowroad.blogspot.com/ ; through Facebook at Willow Road Construction Project; or through Twitter at @willowroadcp.

Please note that the actual start dates and activities may change due to weather, utility, permitting approvals, or other contractor conflicts.   

Wednesday, April 10, 2013

Willow Road Landscape Plans


As the first stage of the Willow Road redevelopment project begins, workers are preparing the landscape for construction.  Trees in conflict with the new roadway have been removed, while other trees, tagged with ribbon, will be protected.  An arborist will prune these trees to maximize their chances for surviving the construction process.

For the new Willow Road, IDOT, the Village of Northfield, Hitchcock Design Group and the Chicago Botanic Gardens developed an extensive landscape plan. In total, 569 new trees, 848 shrubs, and about 11,000 perennials will be installed.  Click here to see the final landscape plan.  The new plantings will provide for:


  • Enhanced gateway medians on the east and west ends of the project
  • Planted medians throughout the corridor
  • Perennial plantings in the medians and at enhanced intersections, and
  • Parkway trees on both sides of the whole roadway


Along with the new plantings the final plan provides for decorative lighting, brick sidewalks, and a decorative stone bridge in the Village Center area. 
To follow the progress of the work and monitor traffic conditions stay tuned to http://northfieldwillowroad.blogspot.com/ on Facebook at Willow Road Construction Project or Twitter @willowroadcp.   

Monday, April 8, 2013

Waukegan Road

Starting April 10th, additional lane closures will be put into effect on Waukegan Road (Route 43) between Three Lakes Drive and Westleigh Drive. Traffic delays are expected.

Friday, April 5, 2013

Whats New for Willow Road

 

For April 8 to April 19

At the April 3, 2013 Willow Road coordination meeting IDOT and Lorig Construction provided their proposed construction schedule for the next two weeks.The work planned includes:

Weeks of April 8th & 15t

 

  •  The tree subcontractor, Homer Tree, will continue to remove the remaining trees scheduled to be taken out and replaced with the project.
  •  Utility companies such as Com Ed, Comcast and NICOR will continue their work relocating utilities that are in conflict with the new roadway.
  • The general contractor, Lorig Construction will begin to install erosion control measures to ensure that silt and other debris is not washed away into adjacent properties or waterways; they will be installing the temporary traffic signals at the intersections; and will start removing the existing landscape medians.

 

More detailed construction work and traffic conditions can be tracked at http://northfieldwillowroad.blogspot.com/ ; through Facebook at Willow Road Construction Project; or through Twitter at @willowroadcp.

Please note that the actual start dates and activities may change due to weather, utility, permitting approvals, or other contractor conflicts.

 

Tuesday, April 2, 2013

Lane Closures

Additional lane closures are planned for tomorrow, April 3rd, between Northfield Road and the Eden’s Expressway. The closures are to provide for tree and median removal. Traffic delays are expected.