Friday, April 5, 2013

Whats New for Willow Road

 

For April 8 to April 19

At the April 3, 2013 Willow Road coordination meeting IDOT and Lorig Construction provided their proposed construction schedule for the next two weeks.The work planned includes:

Weeks of April 8th & 15t

 

  •  The tree subcontractor, Homer Tree, will continue to remove the remaining trees scheduled to be taken out and replaced with the project.
  •  Utility companies such as Com Ed, Comcast and NICOR will continue their work relocating utilities that are in conflict with the new roadway.
  • The general contractor, Lorig Construction will begin to install erosion control measures to ensure that silt and other debris is not washed away into adjacent properties or waterways; they will be installing the temporary traffic signals at the intersections; and will start removing the existing landscape medians.

 

More detailed construction work and traffic conditions can be tracked at http://northfieldwillowroad.blogspot.com/ ; through Facebook at Willow Road Construction Project; or through Twitter at @willowroadcp.

Please note that the actual start dates and activities may change due to weather, utility, permitting approvals, or other contractor conflicts.