Tuesday, April 21, 2015

Special Traffic Alert – April 22

On Wednesday, April 22, IDOT will be closing Bristol, Churchill and Eaton Streets for pavement installation.  Dickens Street will remain open and left turns will be permitted in and out of the neighborhood area.  This new traffic configuration is expected to be in place for approximately three weeks.

 Detailed construction work and current traffic conditions can be tracked at http://northfieldwillowroad.blogspot.com/; through Facebook at Willow Road Construction Project; or through Twitter at @willowroadcp.   Please note that the actual start dates and activities may change due to weather or other conflicts.  #willowroadcp 

Monday, April 20, 2015

Willow Road Work Plan

April 20 – May 4, 2015

Waukegan to Sunset Ridge Road.   The center median work, left turn lanes, and electrical, and landscaping work are all underway in this area.

Sunset Ridge to Wagner.   The roadway pavement is now complete in this section and work will continue on the curb and gutter, landscape restoration, and sidewalks.

Wagner to Bosworth.  Earthwork and subgrade operations will take place as weather permits.  The first pavement installation is expected to start the week of April 27th.  During these operations, access to Churchill, Dickens Eaton and Bristol may be restricted, but one road with left turn out access will, remain open for local traffic at all times.

River Bridge.  The parapet wall, pilasters and railing installation work will all continue. 

Bridge to Happ.  The water main work will take place on Alice Place followed by the final storm sewer and water main connections.  When this work is completed, the contractor will start the earthwork and subgrade operations.

 

The detailed construction work and traffic conditions can be tracked at http://northfieldwillowroad.blogspot.com/ ; through Facebook at Willow Road Construction Project; or through Twitter at @willowroadcp.   

Friday, April 10, 2015

Special Traffic Alert – April 10 - Northfield/Old Willow Road

IDOT is instituting a new traffic configuration today which further impacts the Northfield Road intersection.  The north lanes of Northfield/Old Willow Road will remain open but the left hand turn lane from Willow Road onto Old Willow/Northfield will be under construction.  Motorists can still make left turns, but will have to do so from the through lane.  The traffic signal timing is being adjusted to help minimize the impacts and local traffic is urged to use Wagner Road as an alternative.   The left turn limitations are anticipated to be in effect for one week.                

Detailed construction work and current traffic conditions can be tracked at http://northfieldwillowroad.blogspot.com/; through Facebook at Willow Road Construction Project; or through Twitter at @willowroadcp.   Please note that the actual start dates and activities may change due to weather or other conflicts.  #willowroadcp 

Wednesday, April 1, 2015

Willow Road Detours and Work Plan

April 1 – April 18, 2015

Northfield Detour.  The southern intersection of Willow Road and Northfield Road remains closed for the utility and final pavement installation.  The intersection is anticipated to be re-opened by April 18th.  Local traffic is being detoured east to Happ Road.  Click here to see the detour route: http://www.northfieldil.org/E-News/Northfield_Road_Detour.pdf

Waukegan to Sunset Ridge Road.   The center median work, left turn lanes, and electrical, and landscaping work are all underway in this area.

Sunset Ridge to Wagner.   The roadway pavement was completed this week and the contractor will next be working on the curb and gutter, landscape restoration, and sidewalks.

Wagner to Bosworth.  Earthwork and subgrade operations will take place as weather permits.  The pavement installation will start immediately after that work is completed.  Pavement work could start as early as April 13th.  During these operations, access to Churchill, Dickens and Eaton will be restricted, at times, but Bristol and Wagner Road will remain open to local traffic.

River Bridge.  The parapet wall, pilasters and railing installation work is all underway. 

Bridge to Happ.  The utility installation is ongoing between the Bridge and Northfield Road.  In addition, the contractor will be working on the Northfield Road intersection pavement.

The detailed construction work and traffic conditions can be tracked at http://northfieldwillowroad.blogspot.com/ ; through Facebook at Willow Road Construction Project; or through Twitter at @willowroadcp.   

 

Actual start dates and activities may change due to weather or other conflicts.   #willowroadcp