Monday, April 20, 2015

Willow Road Work Plan

April 20 – May 4, 2015

Waukegan to Sunset Ridge Road.   The center median work, left turn lanes, and electrical, and landscaping work are all underway in this area.

Sunset Ridge to Wagner.   The roadway pavement is now complete in this section and work will continue on the curb and gutter, landscape restoration, and sidewalks.

Wagner to Bosworth.  Earthwork and subgrade operations will take place as weather permits.  The first pavement installation is expected to start the week of April 27th.  During these operations, access to Churchill, Dickens Eaton and Bristol may be restricted, but one road with left turn out access will, remain open for local traffic at all times.

River Bridge.  The parapet wall, pilasters and railing installation work will all continue. 

Bridge to Happ.  The water main work will take place on Alice Place followed by the final storm sewer and water main connections.  When this work is completed, the contractor will start the earthwork and subgrade operations.

 

The detailed construction work and traffic conditions can be tracked at http://northfieldwillowroad.blogspot.com/ ; through Facebook at Willow Road Construction Project; or through Twitter at @willowroadcp.