Thursday, December 4, 2014

Willow Road Detours and Work Plan

December 5 – December 19, 2014

  • Wagner Detour.  The southern intersection of Willow Road and Wagner Road remains closed.   Regional traffic is being detoured to Waukegan Road.  The intersection is anticipated to be re-opened the week of December 22.  Click here for the detour map: http://www.northfieldil.org/documents/Willow/Exhibits/Wagner_Road_Detour_111114.pdf
  • Sunset Ridge Road Intersection.    The intersection remains open to north and south bound traffic but, the no left turn restrictions continue.  The intersection is anticipated to be fully re-opened the week of December 15.
  • Chapel Hill to the River.  The final water, sanitary, and storm sewer installations are all underway and this work will continue over the next two weeks.  Local streets may be impacted periodically for the utility connections within the intersections.
  • River Bridge.  The bridge paving work is scheduled to start the week of December 8.  Once the deck is poured the contractor will start on the parapet wall.
  • Bridge to Edens.  Nicor is still working on this area to remove their gas main that is in conflict with other utilities.  As soon as their work is complete and the contractor can access the area they will begin the water and sewer installations.
  • Edens Bridge to Linder.  The bridge parapet wall and the sidewalk east of the Edens will be poured as weather permits.

The detailed construction work and traffic conditions can be tracked at http://northfieldwillowroad.blogspot.com/ ; through Facebook at Willow Road Construction Project; or through Twitter at @willowroadcp.   As always, actual start dates and activities may change due to weather or other conflicts.   #willowroadcp