Thursday, July 24, 2014

Willow Road Work

July 25 to August 8, 2014

  • Detour - Sunset Ridge IntersectionThe south leg of the Sunset Ridge Road intersection will be closed during this two week period.  Click here to see the detour route http://www.northfieldil.org/documents/Willow/Exhibits/SunsetRidgeDetour.pdf
  • Waukegan Road.  The pavement on the south side of the intersection will be installed over the next week followed by the curb and gutter and the median.
  •  Waukegan to Sunset Ridge.  The curb and gutter and sidewalk work are scheduled to be installed.
  • Sunset Ridge to Chapel Hill.  They expect to finish the installation of the storm sewer and subgrade material and then start pavement work the first week in August.
  • Chapel Hill to the River.  The sidewalks, grading, and seeding are all expected to be completed.
  • Bridge.  The contractor will be finishing the parapet, pilasters, and pedestrian railing.
  • River to the Eden’s.  They plan to finish the earth and subgrade work and then start on the pavement the first week in August. 

The planned operations involve the continued detour on the south side of Sunset Ridge Road. 

 

The detailed construction work and traffic conditions can be tracked at http://northfieldwillowroad.blogspot.com/ ; through Facebook at Willow Road Construction Project; or through Twitter at @willowroadcp.   As always, actual start dates and activities may change due to weather or other conflicts.   #willowroadcp