Over the next two weeks the following construction work is planned:

• From Chapel Hill Lane west, the contractor will install the new drainage and utilities and then begin grading and subgrade operations on the south side of the right of way.

• On Waukegan Road, the contractor will finish the pavement installation for the northwest corner lanes and then install the curb and gutter.

• From Chapel Hill to the river, the contractor will be starting the pavement installation followed by the curb and gutter.

• At the bridge, the contractor will be installing the concrete deck and sidewalls.

• From the river east, the contractor will finish the drainage installation and start grading operations.

• On the Eden’s Expressway the contractor will continue to remove the existing shoulder and unsuitable materials and then install the drainage.

The traffic staging for this work is already in place and no substantial delays are anticipated. More detailed construction work and traffic conditions can be tracked at http://northfieldwillowroad.blogspot.com/ ; through Facebook at Willow Road Construction Project; or through Twitter at @willowroadcp.

Please note that the actual start dates and activities may change due to weather or other conflicts. #willowroadcp