April 18 to May 2, 2014

Over the next two weeks the following construction work is planned:

  • From Sunset Ridge Road west, NICOR will be finishing up their main connection and backfilling the trench excavations.  Immediately following that, the contractor will being the pavement removal on the south side of the right of way followed by grading and subgrade installation.
  • From Wagner to the river the contractor will be finishing up the drainage installation and then begin working on the grading and subgrade installation.
  • At the river, the contractor will begin the installation of the abutment production piles for the bridge as soon as the water levels drop.
  • From the river east, the contractor will be continuing with the utility installation including the new water sanitary and drainage systems.  When that work is complete they will start the grading and subgrade installation.

All of the traffic staging for this work is already in place and no substantial delays are anticipated.  More detailed construction work and traffic conditions can be tracked at http://northfieldwillowroad.blogspot.com/ ; through Facebook at Willow Road Construction Project; or through Twitter at @willowroadcp.   

 

Please note that the actual start dates and activities may change due to weather or other conflicts.   #willowroadcp