Thursday, May 14, 2015

Willow Road Work Plan

May 15-29, 2015

Waukegan to Sunset Ridge Road.   The parkway landscaping work will continue and the median irrigation system installation will commence.

Sunset Ridge to Wagner.   The contractor will be working on the final grading, parkway plantings, curb and gutter, and sidewalks on the south side. 

Wagner to Bosworth.  Churchill, Eaton and Bristol are anticipated to re-open by Monday, May 18.  Immediately thereafter, Dickens Street will be closed and they will start pavement installation within that intersection.  Over the next two weeks the remaining south side curb work will take place along with final parkway grading and plantings.    

River Bridge.  The contractor will be finishing up most of the south side bridge work and is in the process of installing the final pilaster and guard rail system.    

Bridge to Happ.  The contractor will be working on the south side pavement lanes between the bridge and Happ followed by curb and gutter and parkway restoration.  The only remaining intersection work in this area is at Alice Place.  That intersection will be installed in two phases to ensure access is maintained.

Eden’s to East Limits.  Final sidewalk, curbs, and driveway installations will be completed and coordinated in conjunction with other similar work along the corridor.  

 

The detailed construction work and traffic conditions can be tracked at http://northfieldwillowroad.blogspot.com/ ; through Facebook at Willow Road Construction Project; or through Twitter at @willowroadcp.   Actual start dates and activities may change due to weather or other conflicts.   #willowroadcp