Monday, May 4, 2015

Willow Road Work Plan

May 4 to May 18, 2015

Waukegan to Sunset Ridge Road.   Final center median work, electrical, and landscaping work are planned.

Sunset Ridge to Wagner.   The phase III center median work, landscape restoration, and sidewalks are planned.

Wagner to Bosworth.  On Tuesday, May 5th the second lane pavement pour is planned followed by curb and gutter installations and parking way planting on the north side.  Until this work is completed, Churchill, Eaton and Bristol will be closed.  Neighborhood access will remain at Dickens or off of Wagner Road. 

River Bridge.  The parapet wall, pilasters and railing installation work will all continue. 

Bridge to Happ.  The final water main connections will be made and the water will need to be shut off, to certain areas, for short periods of time.  On Tuesday, May 5, a water shut off is scheduled at Northfield Road from 6am to 10am.  This will impact Mariano’s and the businesses along Northfield Road.  When this work is completed, the contractor will start the earthwork and subgrade operations from Northfield to the bridge.  The pavement installation in this area is expected to start by May 11.   

 

The detailed construction work and traffic conditions can be tracked at http://northfieldwillowroad.blogspot.com/ ; through Facebook at Willow Road Construction Project; or through Twitter at @willowroadcp.   Actual start dates and activities may change due to weather or other conflicts.   #willowroadcp