Willow Road Work Plan

July 27 to August 6, 2015

The contractor is working on the Phase III center median and left turn lanes throughout the corridor. This includes pavement removal, curb and gutter installation, left turn pavement, permanent signage, traffic signal installation, pavement markings, and irrigation system installation. Signal work is continuing.

The signals at Waukegan Road have been activated and the ones at Three Lakes Drive are awaiting ComEd connections. The signal contractor is proceeding east along the corridor with the installation and will be working on Sunset Ridge and Wagner over the next two weeks. The permanent signals are planned to be activated once fully installed and then the contractor will remove the temporary devices. The final signal interconnect work will take place at the end of the project after all signals have been activated.

The detailed construction work and traffic conditions can be tracked at http://northfieldwillowroad.blogspot.com/ ; through Facebook at Willow Road Construction Project; or through Twitter at @willowroadcp. Actual start dates and activities may change due to weather or other conflicts. #willowroadcp